September 29, 2026
Budget a renovation in four parts: the design project (typically 8–12% of the total), construction work, materials and fixtures, and furniture with appliances. Then add a 10–15% reserve. Most overruns don't come from prices rising. They come from decisions made on site, redoing work, and items nobody listed. A good budget is mostly a good list.
House renovation cost per m² (or per sq ft in the UK) varies too much by country to quote a universal number. What doesn't vary is the structure, and that's what this article is about.
| Part | What's inside | Typical share |
|---|---|---|
| Design project | Layouts, visualizations, drawings, specification | 8–12% |
| Construction work | Demolition, walls, electrics, plumbing, plastering, tiling, flooring | the largest share |
| Materials and fixtures | Tiles, flooring, paint, sanitaryware, doors, lighting | depends on the specification |
| Furniture and appliances | Kitchen, wardrobes, beds, sofas, white goods | often underestimated |
| Reserve | For what the walls reveal | 10–15% |
Shares for construction, materials and furniture depend on country and choices more than on anything a designer can promise. The design share and the reserve are the two numbers you can plan with confidence.

Example. In the 82 m² apartment in Kyiv the kitchen runs to the ceiling, appliances sit behind the fronts and the light is under the upper cabinets, so no ceiling fitting was needed above the worktop. Each item is in the specification, so it can be priced in advance.
Decisions made on site. The builder asks where the socket goes. You guess, on the phone, from another city. Multiply by a hundred.
Redoing. The kitchen arrives and doesn't fit because a wall was plastered 3 cm thicker than planned. The shower tray doesn't line up with the tile grid. Each fix is small; together they are the overrun.
Missing items. Nobody put skirting boards, door handles, ventilation grilles or the underfloor heating thermostat on the list. They get bought last, fast and expensive.
Scope creep. "While we're at it, let's also…" — every time without a drawing, and without a new number.
In our experience, renovations without a project often run 20–30% over. That figure comes mostly from the four points above, not from inflation.
A budget is only as accurate as the list behind it. A design project produces that list:
The project fee is visible. The savings are the problems that never happen, which is why they're easy to underestimate.


An 80 m² apartment at our rates:
If that €4,000 is about 10% of the renovation, the total is around €40,000. A 20% overrun on that is €8,000 — twice the project fee. The arithmetic only works in the project's favour if the project is used: builders quote from the drawings and buy from the specification.
Is 8–12% for design expensive? Compared with the overruns it prevents, usually not. And you can start with the layout only, which is a fraction of that.
Can the designer design to my budget? Yes, if you name the number at the start. Materials and products are then chosen to fit it, with cheaper equivalents where they matter least.
What's the minimum project? At our studio the minimum is about 50 m². See pricing and how much an interior designer costs.
Request received
Thank you! We've received your request
We respond within one business day. Want it faster? Message us on WhatsApp — we're almost always there.
In the meantime, take a look at what we've already built: interiors · architecture
Clients
Restaurants, hotels, developers, and private clients — 1,172+ projects across 48 countries.



























We’ll reply on WhatsApp or Telegram — no obligation.
or leave your number — we’ll call you back